Cream clapboard house with a covered porch, fieldstone foundation and autumn maple beside a front lawn.

Central Grade's Three-Year Rebuild Is Designed Around What the Neighborhood Wanted to Keep

"Very, very important to the entire community." That is how architect John Dancer of Cornerstone Architects described keeping Central Grade's front lawn when trustees reviewed the reconstruction plans in February, as The Ticker reported. The lawn is still there. Behind it, 301 Seventh St. is now a construction site, and it will stay one until 2029.

The plan is easy to read once you see it as a series of trade-offs. Again and again, the design team gave up some convenience inside the project so the neighborhood would keep what it sees from the sidewalk. Most of the real change happens toward the back of the block and inside the walls.

The Lawn Cost the School Parking

Central Grade sits on a tight site, and every square foot of it was spoken for. Expanding parking was the obvious need. The plan adds only 10 to 12 spaces. TCAPS Assistant Superintendent Christine Thomas-Hill told trustees that this still isn't enough for the whole staff, and that staff supported the trade-off to preserve the front lawn, according to The Ticker.

The lawn won't be untouched. The plan creates one consolidated entrance with a security vestibule on Seventh Street and makes a slight grading change so the entry is ADA accessible without stairs. Still, the broad green front that faces Seventh Street stays green, and the school accepted a parking shortfall to keep it that way.

The Brick on Eighth Street Set the Truck Route

The same priority shapes how the construction itself runs. Jack Abate of Miller-Davis, the construction management firm, called it a "tight" construction site. He said trucks would use Wadsworth to avoid damaging the brick on Eighth Street, The Ticker reported. Thomas-Hill added that some off-site staging could happen at nearby locations such as Thirlby Field.

The truck route runs on the same logic as the lawn. A three-year project with a heavy truck schedule could have been planned around the shortest route in. This one was planned around keeping the neighborhood's brick street intact. Neighbors on Wadsworth will see more of the traffic, and that is part of the same choice.

The TCAPS renovation page lists landscape and tree preservation, noise control, site standards and vehicle and truck traffic as project topics. It sends neighbors with concerns to [email protected] and says replies may take up to 48 hours.

Inside, the Oldest Details Are Staying

The original three-story building dates to 1922, with additions from the 1930s and 1950s, Thomas-Hill told the Record-Eagle. The building also has a fire in 1934 in its past. The plan keeps much of the existing footprint. Thomas-Hill told the Record-Eagle that the district tried to keep or restore what it could, including:

  • the school bell
  • some of the brass clocks
  • some of the landscaping
  • the decorative tiles in the small gym

"We just want to be able to make sure that people understand that we appreciate the history, and we're trying to preserve it as much as possible where we can," Thomas-Hill told the Record-Eagle.

The small gym shows how that works in practice. It is sunken today. The plan raises it to the level of the main floor and gives it a new use while keeping its tiles. The larger gym goes back to its "original shape and design," architect Gabe Alvey of Diekema Hamann Architecture & Engineering told trustees, and its concrete bleachers will be removed.

Lars Hockstad Auditorium Gets Air Conditioning, Not a Makeover

For neighbors who never had a reason to walk the halls, Lars Hockstad Auditorium is the part of Central Grade they know best. The plan leaves it mostly as it is, with minor code updates. The one big change is that the building, auditorium included, will have air conditioning for the first time in its history. A design plan described by the Record-Eagle adds secure doors so public events in the auditorium can be kept separate from the school.

Those doors fit the pattern, keeping the auditorium available for public events while the classrooms stay secure.

A Third Floor Closed Since 1970 Comes Back

One floor is changing more than any other. Central Grade's third floor has been closed since 1970 because of hazards such as asbestos, Superintendent John VanWagoner told the Record-Eagle. The renovation cleans and updates it, and its first planned use is professional development. The Ticker reported that the third-floor conference rooms can be set up for groups of different sizes and turned into classrooms later if Central Grade grows.

The building's top floor has been sealed off for 56 years, and this rebuild is meant to put it back in use.

The Back of the Block Is Where the Building Changes

The west wing and the Eighth Street side carry most of the change. Part of the west wing will be demolished and replaced with a new two-story addition. A new cafeteria and kitchen will sit closer to Eighth Street at the back of the building, with direct access to the playground.

The playground will be fully fenced and surfaced with wood chips, and students will no longer cross a service drive to reach parts of it. Thomas-Hill described the result as "a little bit smaller but much more usable and friendly." The Record-Eagle also reported an added drop-off loop.

Seen from Seventh Street, Central Grade in 2029 should look much like the building neighbors already know. Seen from Eighth Street, it will look much more different.

The Money and the Calendar

Voters approved the TCAPS capital bond on August 6, 2024, by 14,196 to 7,816, according to Record-Eagle results. The $180 million proposal included the Central Grade reconstruction, as TCAPS announced ahead of the vote. In July 2026, trustees approved more than $42.1 million in contracts, including a 15% contingency tied to the building's age, the Record-Eagle reported. The total project is expected to cost about $51 million, down from the original $55 million estimate.

TCAPS's August 2026 district newsletter said construction had officially begun. Thomas-Hill presented the schedule below at the Central Neighborhood Association's June 17, 2026 meeting. It is the project's planned sequence:

Month, 2026 Planned work
August Abatement and demolition, utility changes
September Abatement, removal of building structure, utility coordination
October Demolition, finish abatement, prepare for earthwork and foundation
November Begin excavation, build foundation
December Finish foundation, begin putting up structural steel

November is when the plan calls for digging and foundation work. If the schedule holds, December is when the steel frame starts going up. TCAPS has said it expects substantial completion by June 2029 and a reopening for the 2029–30 school year. An earlier February report gave May 2029. Students and staff are spending the three years at Glenn Loomis on Oak Street.

Following the Work From Your Porch

At the June meeting, the Central Neighborhood Association said its president, Matt Hanley, would receive project updates and share them through the association's existing channels. The association's next quarterly meeting is Wednesday, December 2, at 6 p.m. at Crooked Tree Arts Center, 322 Sixth St. That date falls right when the schedule calls for the foundation to finish and the steel to start. Annual dues are $10 per person, and the secretary position is still open for a volunteer.

The association also runs PorchFest, which took its eighth year to porches between Fifth and 13th streets, from Division to Oak, on September 20. Those blocks surround the construction site, so the association already has a way to reach the neighbors who live beside it.

For questions about trucks, noise, trees or anything else at the fence line, email [email protected] and expect a reply within 48 hours.

Hillary has watched the rebuild of this block from the sidewalk, from the front lawn on Seventh Street to the brick on Eighth. If you live near the site or are thinking about what a 2029 Central Grade means for your corner of the neighborhood, Found Realty Co would love to talk it through with you. Find Happiness at Home and schedule a personalized consultation.

Work with a dedicated expert.

Whether you’re buying your first home or searching for the perfect vacation retreat, my expertise and community connections ensure a seamless experience. Let’s turn your dreams into reality!

Follow Me on Instagram